Question: What is the optimal project cost for a 19-week completion schedule? Given the following project data and diagram that represents every activity fully crashed: JActivit

What is the optimal project cost for a 19-week

What is the optimal project cost for a 19-week completion schedule?

Given the following project data and diagram that represents every activity fully crashed: JActivit Normal Time 9 B 6 3 4. E 6 F 8 G 7 H 7 Normal $4,400 $5,200 $4,500 $4,000 $4,200 $3,700 $4.000 $6,000 Crash Time 6 3 3 2 3 4. 5 5 Crash $6,200 $5,800 $4,500 $6,000 $6,600 $5.700 $6.000 $7.500 19 A(6), B(3), G(5), H(5) C(3),E(3),F(4), H(5) 15 C(3),D(2),F(4), H(5) 14