Question: Given the following project: Develop a resource-constrained schedule using the sequential heuristic. Activity Predecessor Duration (week) Required No. of Workers A - 1 1 B
- Given the following project:
- Develop a resource-constrained schedule using the sequential heuristic.
|
Activity |
Predecessor | Duration (week) | Required No. of Workers |
| A | - | 1 | 1 |
| B | - | 3 | 2 |
| C | A | 4 | 2 |
| D | A,B | 5 | 1 |
| E | B | 3 | 2 |
| F | C,D,E | 2 | 2 |
Assume the followings:
- The original sequential relationships of the network cannot be violated.
- An activity can be scheduled at any time between the ES and LS times
- Scheduling priority for each activity is determined via the following rules
- early start time
- least total slack
- smallest duration
- maximum resource level
- once an activity is scheduled it continues without interruption
The available resource is three workers.