Question: Given the following project: Develop a resource-constrained schedule using the sequential heuristic. Activity Predecessor Duration (week) Required No. of Workers A - 1 1 B

  1. Given the following project:
  1. Develop a resource-constrained schedule using the sequential heuristic.

Activity

Predecessor

Duration

(week)

Required No.

of Workers

A

-

1

1

B

-

3

2

C

A

4

2

D

A,B

5

1

E

B

3

2

F

C,D,E

2

2

Assume the followings:

  • The original sequential relationships of the network cannot be violated.
  • An activity can be scheduled at any time between the ES and LS times
  • Scheduling priority for each activity is determined via the following rules
  • early start time
  • least total slack
  • smallest duration
  • maximum resource level
  • once an activity is scheduled it continues without interruption

The available resource is three workers.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!