Question: Given the following project network: a - 1 . Identify the critical path. multiple choice A - C - D - F A - B

Given the following project network:
a-1. Identify the critical path.
multiple choice
A-C-D-F
A-B-D-F
A-C-E-F
a-2. Identify the earliest start and finish for each task. (Leave no cells blank - be certain to enter "0" wherever required.)
b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "0" wherever required.)