Question: Given the following project network, baseline, and status information. 1) Report the final for the entire project a). EV. Assume project completes after period 8.

Given the following project network, baseline, and status information.

1) Report the final for the entire project a). EV. Assume project completes after period 8.

2)Calculate SV for the entire project at the end of period 8

3) Calculate CV for the entire project at the end of period 8

4) Calculate CPI for the entire project at the end of period 8

5)Calculate PCIB for the entire project at the end of period 8

Given the following project network, baseline,Given the following project network, baseline,Given the following project network, baseline,Given the following project network, baseline,Given the following project network, baseline,

Schedule Information Baseline Budget Needs($000) Act/WP Dur ES LF SL Total PV Time period 1 2 3 4 5 6 1 2 0 3 1 12 4 8 2 3 0 3 O 15 3 7 5 3 0 2 0 8 4 4 4 2 5 1 6 3 3 Co N N N 5 3 5 O 10 6 4 6 2 5 O 9 3 3 3 1 7 5 6 0 5 5 Total PV by period 12 11 19 11 7 5 Cumulative PV by period 53 60 65 11 30 41 Time left 1:35:04 DELL Total PV by period Cumulative PV by period 11 19 11 12 75 11 30 41 53 60 65 Status Report: Ending Period 1 Status Report: Ending Period 1 Task % Complete EV AC PV CV SV 50% 6 4 40% 8 3 3 25% 3 4 17 11 Cumulative Totals w Status Report: Ending Period ($000) 2 AC EV PV CV Task SV % Complete Finished 13 12 1 14. 10 2 80% 8 8 3 75% 35 30 Time left 1:34:51 DLL Status Report: Ending Period 2 ($000) Task % Complete EV AC 1 PV CV Finished SV 13 12 2 80% 14 10 3 75% 8 8 Cumulative Totals 35 30 Status Report: Ending Period 3 ($000) Task % Complete EV AC PV CV SV 1 Finished 13 12 80% 15 15 3 Finished 10 8 4 50% 4 5 0% 0 w o w 33.3% 4 46 41 Time left 1:34:42 DOLL 4 XC Status Report: Ending Period 4 ($000) Task % Complete EV AC PV CV SV 1 Finished 13 12 2 Finished 18 15 3 Finished 10 8 Finished 8 6 5 30% 3 6 6 66.7% 8 6 Status Report Ending Period 6 ($000) AC PV CV SV Task EV % complete A 100 35 100 24 B 24 C 75 0 D 0 10 E 50 93 Cumulative Totals ($000) Time left 1:34:34 t: Ending Period 8 DELL Moodle X 6 X CIO Status Report Ending Period 6 ($000) Task % complete EV AC PV CV 100 SV 35 B 100 24 C 75 24 D 0 0 E 50 10 Cumulative Totals 93 Status Report: Ending Period 8 ($000) Task % complete EV AC PV CV SV A 100 35 B 100 24 C 100 32 33 20 E 100 20 131 Cumulative Totals Time left 1:34:28 DLL Schedule Information Baseline Budget Needs($000) Act/WP Dur ES LF SL Total PV Time period 1 2 3 4 5 6 1 2 0 3 1 12 4 8 2 3 0 3 O 15 3 7 5 3 0 2 0 8 4 4 4 2 5 1 6 3 3 Co N N N 5 3 5 O 10 6 4 6 2 5 O 9 3 3 3 1 7 5 6 0 5 5 Total PV by period 12 11 19 11 7 5 Cumulative PV by period 53 60 65 11 30 41 Time left 1:35:04 DELL Total PV by period Cumulative PV by period 11 19 11 12 75 11 30 41 53 60 65 Status Report: Ending Period 1 Status Report: Ending Period 1 Task % Complete EV AC PV CV SV 50% 6 4 40% 8 3 3 25% 3 4 17 11 Cumulative Totals w Status Report: Ending Period ($000) 2 AC EV PV CV Task SV % Complete Finished 13 12 1 14. 10 2 80% 8 8 3 75% 35 30 Time left 1:34:51 DLL Status Report: Ending Period 2 ($000) Task % Complete EV AC 1 PV CV Finished SV 13 12 2 80% 14 10 3 75% 8 8 Cumulative Totals 35 30 Status Report: Ending Period 3 ($000) Task % Complete EV AC PV CV SV 1 Finished 13 12 80% 15 15 3 Finished 10 8 4 50% 4 5 0% 0 w o w 33.3% 4 46 41 Time left 1:34:42 DOLL 4 XC Status Report: Ending Period 4 ($000) Task % Complete EV AC PV CV SV 1 Finished 13 12 2 Finished 18 15 3 Finished 10 8 Finished 8 6 5 30% 3 6 6 66.7% 8 6 Status Report Ending Period 6 ($000) AC PV CV SV Task EV % complete A 100 35 100 24 B 24 C 75 0 D 0 10 E 50 93 Cumulative Totals ($000) Time left 1:34:34 t: Ending Period 8 DELL Moodle X 6 X CIO Status Report Ending Period 6 ($000) Task % complete EV AC PV CV 100 SV 35 B 100 24 C 75 24 D 0 0 E 50 10 Cumulative Totals 93 Status Report: Ending Period 8 ($000) Task % complete EV AC PV CV SV A 100 35 B 100 24 C 100 32 33 20 E 100 20 131 Cumulative Totals Time left 1:34:28 DLL

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!