Question: Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate
Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate the forecasted estimate at completion (EAC) and the forecasted variance at completion (VAC). Based on your data, what is your assessment of the current status of the project? Is it at completion?
look below for attachment show work thanks