Question: Given the following small project for an AOA network, table [ [ Activity , Immediate Predecessor ( s ) , Time Duration ( days

Given the following small project for an AOA network,
\table[[Activity,Immediate Predecessor(s),Time Duration (days)],[A,None,10],[B,None,2],[C,A, E,9],[D,None,3],[E,B, D,5]]
How many dummy arc(s) should be there in this AOA totally?
Select one:
a. one dummy arc
b. two dummy arcs
c. four dummy arcs
d. no dummy arc