Question: Given the following task time estimates ( HOURS ) , Task Time Predecessor A 4 0 B 2 0 C 2 5 A D 1

Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D F 24 E G 18 F a. How long is the project length? [blank1], and what tasks form the critical path? [blank2] Length hours Crit. Path b. What is the LS/LF for activity D.?[blank3]. LS hours LF hours c. How much slack does activity B have? [Blank4] hours d. How much slack is there in activity C?[Blank5] How much slack in activity D?[Blank6] Act. C Slack hours Act. D Slack hours e. What if activity D. was delayed by 6 hours, what would be the project length [Blank7] and critical path? [Blank8] Crit. Path