Question: Given the following task time estimates ( HOURS ) , Task Time Predecessor A 4 0 B 2 0 C 2 5 A D 1
Given the following task time estimates HOURS Task Time Predecessor A B C A D A B E C D F E G F a How long is the project length? blank and what tasks form the critical path? blank Length hours Crit. Path b What is the LSLF for activity Dblank LS hours LF hours c How much slack does activity B have? Blank hours d How much slack is there in activity CBlank How much slack in activity DBlank Act. C Slack hours Act. D Slack hours e What if activity D was delayed by hours, what would be the project length Blank and critical path? Blank Crit. Path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
