Question: Given the following task time estimates ( HOURS ) , TaskTimePredecessorA 4 0 B 2 0 C 2 5 AD 1 9 A , BE

Given the following task time estimates (HOURS),
TaskTimePredecessorA40B20C25AD19A, BE25C, DF24EG18F
a. How long is the project length? [ Select ]["134.83","122.00","127.45","135.78","132.00"].
b. What tasks form the critical path? [ Select ]["A, D, E, F, G","B, D, E, F, G","A, C, E, F, G","A, B, C, E, F, G","B, C, D, E, F, G"]
c. What is the LS/LF for activity D.?[ Select ]["44 and 55","65 and 90","46 and 65","50.19 and 7.08","34.56 and 4.78"].
d. How much slack is there in activity C?[ Select ]["12 hours", "0","8.34 hours", "29 hours", "6 hours"] How much slack in activity D?[ Select ]["6 hours", "28 hours", "0, it is on the critical path", "26 hours", "5 hours"]
e. What if activity D. was delayed by 7 hours, what would be the project length and critical path? [ Select ]["no change in either the critical path or project length", "132 hours; A, C, E, F, G","133 hours; A, D, E, F, G","134 hours; A, C, E, F, G","130 hours; B, C, E, F, F"]
f. Referring to letter e., how much slack would be in activity B.?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!