Question: Given the following: The three estimated work duration - in weeks (a, m, and b) for tasks A, B and C are as shown below:

Given the following: The three estimated work duration - in weeks (a, m, and b) for tasks A, B and C are as shown below: A = 8, 11, 14 B = 7, 10, 19 C = 10, 19, 22 (NOTE - you can open and use an Excel spreadsheet for your calculations for this problem)

The expected time te for each task is as follows A= 11.0 B = 11.0 C = 18.0

The expected time te for each task is as follows A= 11.0 B = 12.0 C = 18.0

For the whole project to complete with 50% probability is 40 weeks

For the whole project to complete with 50% probaility is 42 weeks