Question: Given the information below, Activity Days Immediate Predecessor A 7 B B 2 NONE C 3 A D 5 A E 7 B F 3
Given the information below,
Activity Days Immediate Predecessor
A B
B NONE
C A
D A
E B
F C
G D
H E F
I G H
a Using the enumeration method, calculate and show all of the paths through the network. pts