Question: HW - 8 Given the information below, Activity Days Immediate Predecessor A 7 B B 2 NONE C 3 A D 5 A E 7

HW-8
Given the information below,
Activity Days Immediate Predecessor
A 7 B
B 2 NONE
C 3 A
D 5 A
E 7 B
F 3 C
G 4 D
H 6 E F
I 5 G H
(a) Create the project schedule network. (5 pts)
(b) Using the two-pass method, calculate and show the early and late starts (10 pts)
(c) float for each activity and the critical path. (5 pts)
(d) Show the schedule on a Gantt chart showing critical and noncritical activities and float. (5 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!