Question: Given the information below Activity Days Immediate Predecessor A 5 - B 2 A C 4 A D 7 A E 3 B F 6
Given the information below
| Activity | Days | Immediate Predecessor |
| A | 5 | - |
| B | 2 | A |
| C | 4 | A |
| D | 7 | A |
| E | 3 | B |
| F | 6 | B, C |
| G | 8 | D, E, F |
Given the information in the table, create a project schedue network using normal time and paste it below. (Draw by hand or use ppt)
Then use the table below to full the results using the two-pass method:
| Activity | Days | Immediate Predecessor | ES | LB | EF | LF | Slack | Critical Path? |
| A | 5 | - | 0 | 0 | 5 | 5 | 0 | yes |
| B | 2 | A | ||||||
| C | 4 | A | ||||||
| D | 7 | A | ||||||
| E | 3 | B | ||||||
| F | 6 | B, C | ||||||
| G | 8 | D, E, F |