Question: Given the network below with precedence and time durations. Activity Immediate Predecessor Time Duration A - 5 B A 8 C B 3 D A

Given the network below with precedence and time durations.

Activity

Immediate Predecessor

Time Duration

A

-

5

B

A

8

C

B

3

D

A

4

E

C

5

F

C

7

G

E, D

6

H

F

8

I

G

6

J

H, I

5

a. Draw the network given properly.

b. Develop all the possible paths.

c. Calculate the Early Start, Late Start, Early Finish and Late Finish per activity.

d. Determine the Total and Free Slack for each activity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!