Question: Given the network below with precedence and time durations. Activity Immediate Predecessor Time Duration A - 5 B A 8 C B 3 D A
Given the network below with precedence and time durations.
| Activity | Immediate Predecessor | Time Duration |
| A | - | 5 |
| B | A | 8 |
| C | B | 3 |
| D | A | 4 |
| E | C | 5 |
| F | C | 7 |
| G | E, D | 6 |
| H | F | 8 |
| I | G | 6 |
| J | H, I | 5 |
a. Draw the network given properly.
b. Develop all the possible paths.
c. Calculate the Early Start, Late Start, Early Finish and Late Finish per activity.
d. Determine the Total and Free Slack for each activity.