Question: Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial
Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now?


\f2 4 C E O 4 3 6 C C Plan 3 3 5 2 C 2-E 5 Develop a loading schedule for each resource below. Carpenter Electrician 0 2 3 4 5 7 8 9 10 11 12 13 14 Fill in the times below for a resource activity schedule. ID/RES ES LS EF LF SL Schedule 1-C Legend 2-C ES ID EF 3-C SL SL 4-E LS DUR LF 5-2-E 6-C Resource