Question: Given the project activity information provided below: a ) Draw the project network. b ) What are the ES , EF , SL , LS

Given the project activity information provided below:
a) Draw the project network.
b) What are the ES, EF, SL, LS, and LF for each of the nodes in the network? (Given ID, DUR, and Description.)
c) What is the critical path?
\table[[Activity (ID),Description,\table[[Preceding],[Activity]],\table[[Activity Time],[(DUR)]]],[1,Requirements,None,18],[2,Architecture,1,10],[3,Design C,2,15],[4,Design S,2,18],[5,Design M,2,16],[6,Coding U,3,8],[7,Coding T,4,5,9],[8,Coding N,5,7],[9,Integration I,6,7,8],[10,Integration J,7,8,9],[11,System,9,10,10]]
Grading Rubric
a) Wrong network (nodes, dependencies),-25 points
b) Wrong value for ES, EF, SL, LS, or LF,-1 point each... and they will cascade (55 points total)
c) Wrong critical path, -20 points
 Given the project activity information provided below: a) Draw the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!