Question: Given the project activity information provided below: a ) Draw the project network. b ) What are the ES , EF , SL , LS
Given the project activity information provided below:
a Draw the project network.
b What are the ES EF SL LS and LF for each of the nodes in the network? Given ID DUR, and Description.
c What is the critical path?
tableActivity IDDescription,tablePrecedingActivitytableActivity TimeDURRequirements,None,Architecture,Design CDesign SDesign MCoding UCoding TCoding NIntegration I,Integration JSystem,
Grading Rubric
a Wrong network nodes dependencies points
b Wrong value for ES EF SL LS or LF point each... and they will cascade points total
c Wrong critical path, points