Question: Given the project data below, what is the standard deviation of durations for path A , B , C ? table [ [ Task

Given the project data below, what is the standard deviation of durations for path A,B,C?
\table[[Task,Predecessors,\table[[Best],[Case]],\table[[Most],[Likely Case]],\table[[Worst],[Case]]],[A,None,2,4,6],[B,A,1,4,5],[C,B,.5,1,6]]
A.1.4
B.2.3
C.1.7
D. None of the choices is correct
 Given the project data below, what is the standard deviation of