Question: Given the project in the table below, estimate the expected duration of the project and the probability of completing this project in 63 days or

Given the project in the table below, estimate the expected duration of the project and the probability of completing this project in 63 days or less. Consider the cumulative probability of a Z-score value beyond 3.99 with 1.0. The solution should include the following procedures: 1) mean and standard deviation for each activity and 2) mean, standard deviation, and probability at each path (also called chain), and 3) a final answer. (Note: Use the end-of-day convention.)Given the project in the table below, estimate

\begin{tabular}{|c|c|c|c|c|} \hline Activity & IPA & to & tm & tp \\ \hline A & & 4 & 5 & 6 \\ B & A & 10 & 12 & 14 \\ C & A & 7 & 9 & 16 \\ D & B & 14 & 17 & 22 \\ E & B, C & 10 & 15 & 30 \\ F & C & 4 & 7 & 13 \\ G & D & 12 & 20 & 40 \\ H & D, E & 10 & 12 & 15 \\ I & F, H & 8 & 9 & 10 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!