Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 None B 3 None 10 None D 7

Given the project within the table below,
Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 None B 3 None 10 None D 7 B.C E 1 D F 1 E G 5 AF a. What is the project's minimum completion time? Select] b. What is the critical path in the project? Select] c. What is the slack in activity B? [Select) d. What is the Late Start and Late Finish for Activity A? Select] e. What is the Early Start and Early Finish for activity D? Select MacBook Air