Question: Given the resources allocated by the aggregate plan, an operations manager develops a weekly schedule for producing a specific product. Which of the following is
Given the resources allocated by the aggregate plan, an operations manager develops a weekly schedule for producing a specific product. Which of the following is the operations manager creating?
A.short-term schedule
B.master schedule
C.breakdown schedule
D.aggregate schedule