Question: Given the small project for an AOA network:Activity: A , B , C , D , EImmediate Predecessor ( s ) : None, A ,
Given the small project for an AOA network:Activity: A B C D EImmediate Predecessors: None, A None, A BCDTime Duration days: How many dummy arcs is are there in this AOA network? Select one: ABCDE