Question: Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 4 8

Given the time-phased work packages and network,Given the time-phased work packages and network,

Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 4 8 2 2 6 4 10 O 1 1 4 1 5 4 D 10 F 12 5 0 5 10 O 10 NON B 5 10 2 12 O 0 O 5 0 5 5 E 5 2 7 8 2 10 3 Cost by week: A 5 8 B 8 4 81 6 C D Noon 6 20 30 8 4 6 6 6 2 8 8 20 20 2 2 12 E 09 & Enter the appropriate values in the truncated portion of the budget form shown below. Time Periods 4 5 1 6 7 N ** ID Budget A 63 B 32 24 D 18 E 28 F 40 Total 205 Cumulative D