Question: Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 4 2

Given the time-phased work packages and network,

Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 4 2 8 2 10 A 0 1 1 4 1 5 4 5 D F lol + 10 0 10 olul 10 O 10 12 0 12 B 5 5 2 0 0 0 5 0 5 5 E 5 2 7 NIN 8 2 10 3 Cost by week: 8 A B 4 8 C 6 6 20 30 5 8 4 8 6 6 6 6 2 2 8 8 12 20 20 D 2 E Enter the appropriate values in the truncated portion of the budget form shown below. Time Periods 4 5 1 2. 6 7 ID Budget A 63 B 32 24 D 18 E 28 F 40 Total 205 Cumulative