Question: Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 5 C

Given the time-phased work packages and network,Given the time-phased work packages and network,

Given the time-phased work packages and network, complete the baseline budget for the project. Legend ES ID EF SLK SLK LS DUR LF 5 C 8 2 10 7 A 5 0 0 0 5 5 F 5 0 5 10 0 10 10 0 10 12 0 12 a 1 B S 2 1 1 4 1 5 4 4 E NU 2 10 4 Cost by week: 5 3 10 81 A IB 7 4 8 12 C ID 800 NNW 4 5 2 6 E 12 12 8 8 20 20 Enter the appropriate values in the truncated portion of the budget form shown below. Time Periods ID Budget 1 N 4 5 6 7 A 29 B 21 28 D 21 E 40 F 40 Total 179 Cumulative