Given these tasks and estimated durations along a

Given these tasks and estimated durations along a critical path, use the critical chain method to create new estimated durations (on scratch paper) and determine the buffer. What is the buffer size? Original Estimated Duration New Duration Estimate Task A 22 B 12 8 D 14 E 16 F 10 G 26 108 not enough data provided OO 27 o 54