Question: Given this information: Daily demand = 5 0 urits; Standard deviation of diemand = 6 units; and Iead time = 4 days . What is

Given this information: Daily demand =50urits; Standard deviation of diemand =6units; and Iead time =4days. What is the reorder point to attain a service level of 95percent during lead time, assuming that the demand is distributed normally? 240220180160200