Question: Precedence Diagram Method (PDM) Draw the network and calculate the following. 1. Forward Path 2. Backward Path 3. Critical Activities 4. Critical Path 5. Total

Precedence Diagram Method (PDM)

Precedence Diagram Method (PDM) Draw the network

Draw the network and calculate the following. 1. Forward Path 2. Backward Path 3. Critical Activities 4. Critical Path 5. Total Float 6. Free Float 04: IPA Logic Activity ID A Duration 11 15 - B A B 6 D D 5 SS5 SS10, SF5 FFO FF10, FS2 SS10, FS4 FS5 FSO FSO E 14 D F E 5 G B 10 H 5 F G FF5 FS15