Question: Help me, please! Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for

Help me, please!

Help me, please! Develop a solution for the

Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for the set of tasks. b. Calculate the minimum number of workstations. c. Show what tasks are assigned to which stations? Using the heuristic rules d. How much idle time is there, summed over all workstations? e. What is the efficiency of this line? Work Task Immediate Predecessor(s) Task Time (seconds) 70 60 120 60 240 100 190 A B D E F G A B C,D A E, F