Question: Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
| Activity | Immediate Predecessor | Normal Time | Crash Time | Normal Cost | Crash Cost | ||||
| A | None | 3 | 2 | $200 | $450 | ||||
| B | A | 4 | 3 | $300 | $600 | ||||
| C | A | 2 | 1 | $200 | $300 | ||||
| D | B and C | 3 | 2 | $500 | $550 | ||||
| E | D | 3 | 1 | $500 | $900 | ||||
a. What are the total time of this project?
b. What is the total crash cost?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
