Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. . ABCD A.E.G.C.D A.E.F.D b. How many weeks will the
Here is a CPM network with activity times in weeks: a. Determine the critical path. . ABCD A.E.G.C.D A.E.F.D b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration
Step by Step Solution
There are 3 Steps involved in it