Question: Problem 5-14 Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-E-F-C-D A-E-F-D A-B-C-D b. How many weeks

Problem 5-14 Here is a CPM network with activity

Problem 5-14 Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-E-F-C-D A-E-F-D A-B-C-D b. How many weeks will the project take to complete? Number of weeks