Question: can someone help me out please? Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-B-C-D A-E-F-D b.

Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-B-C-D A-E-F-D b. How many weeks will the project take to complete? b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration