Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-DA-B-C-DA-E-F-D b. How many weeks will the project take to

Here is a CPM network with activity times in

Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-DA-B-C-DA-E-F-D b. How many weeks will the project take to complete