Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. A-E-G-C-D A-E-F-D A-B-C-D A-E-F-C-D b. How many weeks will the

Here is a CPM network with activity times in

Here is a CPM network with activity times in weeks:

a. Determine the critical path.

A-E-G-C-D
A-E-F-D
A-B-C-D
A-E-F-C-D

b. How many weeks will the project take to complete?

Number of weeks

B(8) C(5) A(7) G(3) D19) E(2) F(8)