Douglas College is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information: (5 Marks)
| Activity | Description | Predecessors | Duration (Days) |
| A | Site selection | None | 4 |
| B | Buy concessions | A | 4 |
| C | Rent facilities | A | 2 |
| D | Build stands | A | 5 |
| E | Generator & wiring installation | C | 2 |
| F | Security | B | 4 |
| G | Lighting installation | E | 2 |
| H | Sound system installation | E, F | 2 |
| I | Stage construction | D | 3 |
| J | Tear down | G, H, I | 4 |
- Conduct both a forward and backward pass using AON notation include in your answer. What is the estimated total duration of the project?
- Identify all paths through the network and their durations. Which one is the critical path?
- Which activities have slack time? How much slack?
- Identify all burst activities and merge activities.