Douglas College is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information: (5 Marks)

Activity

Description

Predecessors

Duration (Days)

A

Site selection

None

4

B

Buy concessions

A

4

C

Rent facilities

A

2

D

Build stands

A

5

E

Generator & wiring installation

C

2

F

Security

B

4

G

Lighting installation

E

2

H

Sound system installation

E, F

2

I

Stage construction

D

3

J

Tear down

G, H, I

4

  1. Conduct both a forward and backward pass using AON notation include in your answer. What is the estimated total duration of the project?
  2. Identify all paths through the network and their durations. Which one is the critical path?
  3. Which activities have slack time? How much slack?
  4. Identify all burst activities and merge activities.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!