Question: How long does it take to finish this project? Activity Immediate predecessor Time (days) A 3 B A 4 C A 6 D B 6

How long does it take to finish this project? Activity Immediate predecessor Time (days) A 3 B A 4 C A 6 D B 6 F 4 F C 4 G D 6 H E.F Select one: O a. 23 days O b. 18 days O c. 21 days O d. 20 days O e. 24 days