Question: The following are the activities for a given project. Activity. Immediate predecessor Time (days) A - 6 B - 4 C A 3 D A

The following are the activities for a given project.

Activity. Immediate predecessor Time (days)

A

-

6

B

-

4

C

A

3

D

A

5

E

A

1

F

B, C

4

G

B, C

2

H

E, F

6

I

E, F

5

J

D, H

3

K

G, I

5

Construct (a) Gantt chart and CPM structure diagram for the above project and also determine:

  1. Earliest start and finish times of each activity

  2. Latest start and finish times of all activities

  3. Critical path and critical activities

  4. Float (slack)

  5. Duration of a project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!