Question: The following are the activities for a given project. Activity. Immediate predecessor Time (days) A - 6 B - 4 C A 3 D A
The following are the activities for a given project.
| Activity. Immediate predecessor Time (days) | ||
| A | - | 6 |
| B | - | 4 |
| C | A | 3 |
| D | A | 5 |
| E | A | 1 |
| F | B, C | 4 |
| G | B, C | 2 |
| H | E, F | 6 |
| I | E, F | 5 |
| J | D, H | 3 |
| K | G, I | 5 |
Construct (a) Gantt chart and CPM structure diagram for the above project and also determine:
-
Earliest start and finish times of each activity
-
Latest start and finish times of all activities
-
Critical path and critical activities
-
Float (slack)
-
Duration of a project