Question: HW #4 (Expediting) Apply time-costing method to this project and answer following questions (5 points). Activity b c. d Predecessors Normal Time | Expected Time

HW #4 (Expediting) Apply time-costing method to

HW #4 (Expediting) Apply time-costing method to this project and answer following questions (5 points). Activity b c. d Predecessors Normal Time | Expected Time | Cost/week | None 5 15000 None 4 3 18000 a,b 12 10 17600 c 10 7 8800 d 8 13600 e 12 5440 e 10 8000 e 8 7000 gh 6 4 8000 a,e,i 4 16000 000 The reward for each week of an earlier completion is $16,000. o How to optimally expedite this project? o What is the optimal gain