Question: i. For a project, the following earned value data have been assessed: (1.0 pts.) AC: $4,000,000 CV: $500,000 SPI: 1.12 Project budget: $9,650,000 What is

i. For a project, the following earned value data

i. For a project, the following earned value data have been assessed: (1.0 pts.) AC: $4,000,000 CV: $500,000 SPI: 1.12 Project budget: $9,650,000 What is the earned value of the project? $5,650,000 $3,500,000 $4,480,000 $3,000,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!