Question: I need answer for question a, b and c. 1. Create a network diagram using ADM (1 mark) PREDECESSOR DURATION (days) NODE NAME START A

I need answer for question a, b and c. 1. Create

I need answer for question a, b and c.

1. Create a network diagram using ADM (1 mark) PREDECESSOR DURATION (days) NODE NAME START A B C D 3 10 5 6 9 E F 4 G H . D E B GI C 5 12 6 - J 00 END a. Find the critical path. For example: START-A-B-C-D-END. Critical path is the path or connected line that has the longest total duration. (1 mark) b. What is the total duration of the project? (1 mark) What is the duration of the critical path? (1 mark) C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!