ICE Assignment
Build a critical path based on the data below
\table[[Activity,Activity Time,Slack],[ES,EF,LS,LF,,],[A,0,2,5,7,5,],[B,0,3,0,3,0,],[C,2,7,7,12,5,],[D,3,12,3,12,0,],[E,12,17,12,17,0,],[F,12,17,14,19,2,],[G,17,19,17,19,0,]]
Determine the early start for each activity.
Build the critical path using the data.
Determine the critical path or longest length through the project.
What is the shortest length the project can be completed?
Slack =LS-ES or Slack =LF-EF