Question: ID (A) Activity (Order review) Predecessor (None) Time (2) ID (B) Activity (order standard parts) Predecessor (A) Time (15) ID (C) Activity (produce standard parts)
ID (A) Activity (Order review) Predecessor (None) Time (2)
ID (B) Activity (order standard parts) Predecessor (A) Time (15)
ID (C) Activity (produce standard parts) Predecessor (A) Time (10)
ID (D) Activity (Design custom parts) Predecessor (A) Time (13)
ID (E) Activity (software development) Predecessor (A) Time (18)
ID (F) Activity (Manufacture custom hardware) Predecessor (C, D) Time (15)
ID (G) Activity (Assemble) Predecessor (B, F) Time (10)
ID (H) Activity (Test) Predecessor (E, G) Time (50)
using AON Diagrams answer the following questions
Calculate the early and late activity times
a) Calculate the critical paths and times in all cases
b) If it asks about slack times, just answer for individual activity slack times. There is no need to distinguish between free and total slack.