ID Description Predecessor "Time
(days)"
A Systems None 7
B Subsystem A design A 2
C Subsystem B design A 2
D Subsystem C design A 2
E Program A B 3
F Program B C 3
G Program C D 3
H Subsystem A E 4
I Subsystem B F 4
J Subsystem C G 4
K Integration H, I, J 3