Question: Identify critical path How many weeks will it take to complete the project? Which activities have slack, and how much? Activity A B C D

  1. Identify critical path 
  2. How many weeks will it take to complete the project? 
  3. Which activities have slack, and how much?
  4. Activity A B C D E F G H Immediate Predecessor A 

Activity A B C D E F G H Immediate Predecessor A A B C,D D F E, G (Time Weeks) 1 4 4 2 5 2 2 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path is A4 CD and G These activities have zero slack because ... View full answer