Question: If a project team is subdividing project work packages into smaller, more manageable components, they are: Decomposing. Creating a WBS _ Network diagramming. Activity sequencing.
If a project team is subdividing project work packages into smaller, more manageable components, they are: Decomposing. Creating a WBS Network diagramming. Activity sequencing.