Question: If an activity whose normal duration is 1 6 days can be shortened to 1 3 days for an added cost of $ 1 ,

If an activity whose normal duration is 16 days can be shortened to 13 days for an added cost of $1,500, what is the crash cost per period?
$750
$15,000
$13,000
$1,500
$500
 If an activity whose normal duration is 16 days can be