Question: If an activity whose normal duration is 15 days can be shortened to 13 days for an added cost of $4,000 to the project, what
If an activity whose normal duration is 15 days can be shortened to 13 days for an added cost of $4,000 to the project, what is the crash cost per period? $500$2,000$1,000$1,500