Question: If Crash Cost is = $ 7 0 0 0 , ?Normal Cost is = $ 4 0 0 0 , ?Normal Time to complete

 If Crash Cost is = $ 7 0 0 0 ,
If Crash Cost is = $ 7 0 0 0 , ?Normal Cost is = $ 4 0 0 0 , ?Normal Time to complete the project is = 1 0 ?weeks and the crash time is = 8 ?weeks, then the cost to crash per week equals:
Select one:
a . ?$ 3 0 0 0
b . ?$ 7 0 0
c . ?$ 1 5 0 0
d . ?$ 3 0 0