Question: If someone could quickly answer these questions PLEASE! My 4th question is a A-d please answer fully :) 1) What is the overall duration of

If someone could quickly answer these questions PLEASE! My 4th question is a A-d please answer fully :) If someone could quickly answer these questions

1) What is the overall duration of the project (in weeks)? 2) What is the project's critical path?

ACFGIJK

ABDGIJK

ABEHJK

3) If activity F were shortened by 3 week(s) and activity H were shortened by 5 week(s), what would be the project's critical path?

ABEHJK

ABDGIJK

ACFGIJK

4) Please answer 4A-D

Activity Duration (weeks) Immediate Predecessor(s)
A 19 -
B 10 -
C 17 A
D 6 B
E 6 D
F 14 A,E
G 1 F
H 7 C,G

A) What is the duration of the project? (weeks)

B) What is the latest start week for activity C?

C) What is the slack time for activity B?

D) If activity E were shortened by 3 weeks, what would be the new duration of the project?

PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition. They want to equip these hospitals with state of the art cancer treatment equipment and train staff to use it. The company has broken this project down into lettered activities and their durations in weeks: Activity Duration (weeks) Immediate Predecessor(s) 12 D,F 10 12 G HU

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!