Question: If the optimistic time for a task is 5 days, the most likely time is 10 days, and the pessimistic time is 15 days, what
If the optimistic time for a task is 5 days, the most likely time is 10 days, and the pessimistic time is 15 days, what is the expected time for the task? Group of answer choices 12 11 10 13