Question: If the optimistic time for an activity is 6 weeks, the pessimistic time is 2 4 weeks and the most likely time is 1 2

If the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and the most likely time is 12 weeks, then the expected completion time (duration) is:
Question 1 options:
13 weeks
7 weeks
14 weeks
24 weeks